Right-of-Way (ROW) Bond Requirements
Bonds are required for Right-of-Way (ROW) permits related to the following activities:
Mitigation, site preparation, and erosion control
Public sidewalk, concrete curb and gutter, and ADA ramp construction
Paving restoration
Placement of equipment in the ROW (e.g., cranes, lifts)
Dewatering discharge offsite
Water, sewer, and sewer lateral work
Stormwater drainage improvements
Note: Additional bond requirements may apply depending on project scope and permit conditions.
Step-by-Step Process
Accepted Bond Types
1. Cash Bond
2. Surety Bond
1. Submit the original bond only - no copies.
2. If the permit is ‘Awaiting Issuance’, notify that the bond has been paid to: PermitIntake@fortlauderdale.gov
3. Refunds are issued only to the original ‘Depositor’.
| Bond Type | Bond Refund / Release Eligibility |
| Dewatering discharge offsite |
Refund eligible upon master permit completion and successful bond inspection. |
| Commercial Erosion and Sediment Control | Refund eligible upon master permit completion and successful bond inspection. |
|
Public Sidewalk construction for Single-Family Residence (SFR) or Duplex |
Refund eligible 30 days after master permit completion and successful bond inspection. |
| Equipment placement on public right-of-way (e.g. crane, lift) | Refund eligible 30 days after master permit completion and successful bond inspection. |
| Other bond types not listed above | Refund eligible 1 year after master permit completion and successful bond inspection. |
Master Permit Completion: Refers to the final status of the primary permit associated with the work.
Special Conditions: Specific projects may have unique requirements or timelines as determined by the City Land Development Manager. These conditions may override the general eligibility periods listed above.
Timeline: Cash bond refunds involve multiple City divisions and may take up to twelve weeks to process from the date the applicant’s complete refund request is received. Processing times may vary based on the volume of requests and required reviews.
1. Confirm eligibility (see above).
2. Submit Request via LauderBuild
a. Login to LauderBuild.
b. Select 'Home' from the top menu bar.
c. Choose 'Fees/Refunds', then 'Refund Request', then 'Engineering Refund Request'
d. Upload receipt as type 'Receipt' - Required to continue
Tip: Can't find your receipt? - Download it from ROW permit - (Record Info - Attachments)
e. Follow online instructions to complete the request and 'Finish' to submit.
3. Address/Name Change: Upload official verification clearly identifying the change from the previous to the new information. Incomplete or unclear documentation may delay processing.
4. Pay Bond Processing Fee
DSD Engineering Administration will review your request and may provide comments or schedule the required bond inspection. Once the request is accepted, it will be routed internally for management review and approval. If additional information is needed, you will be notified through comments posted in the request record. You can check the status of your request anytime, 24/7, through LauderBuild.